Subject: 8.3 Elevator Replacement (Park Hill South)
Strategic Plan:
2023-2028 CSIP GOAL
Build successful futures for Park Hill students of all backgrounds
Policy: FB - Facilities Planning
Provide Name(s) of Attachments Elevator Modernization State Contract
File Attachment:
Park Hill South Elevator Modernization.pdf
MEI State Contract.pdf
Provide Background Details and Rationale: The passenger elevator at Park Hill South High School has reached the end of it's useful life. This project, if approved, will modernize the unit to be more reliable for student and staff use. The project is able to participate under the Missouri State Contract awarded to Minnesota Elevator, Inc. on September 1, 2023.
Provide Funding Source and Estimated Cost: Funding would be provided from the 2023-2024 Maintenance and Operations budget. The total project cost is $124,264.
Legal References N/A
Name of Persons(s) Submitting Agenda Item with Title Jim Rich, Director of Operations Dr. Paul Kelly, Assistant Superintendent for Business and Technology
Presenter(s) if Presentation Anticipated N/A
Recommendation: It will be recommended at the January 11, 2024 Regular meeting that the Park Hill Board of Education approve the Elevator Replacement at Park Hill South, as presented.
Approvals:
Recommended By:
Signed By:
Jim Rich - Director of Operations
Signed By:
Dr. Paul Kelly - Assistant Superintendent - Business & Technology
Signed By:
Dr. Mike Kimbrel - Superintendent