7.2 Planned Asphalt Repairs (Congress, English Landing, Line Creek, Gerner, PHHS, Union Chapel)
|
Strategic Plan:
|
|
Provide Name(s) of Attachments
|
Bid Tab
|
File Attachment:
|
|
Provide Background Details and Rationale:
|
Various areas of the district have been evaluated and identified for asphalt repairs, replacement or additions. Included in the project are four (4) separate packages for bidders to respond.
*Package 1 - Congress
*Package 2 - English Landing
*Package 3 - Line Creek
*Package 4 - (reclamite seal)- Gerner, Park Hill High, Union Chapel
|
Provide Funding Source and Estimated Cost:
|
Funding will be provided from the proposed 2023-2024 Maintenance and Operations budget. The total for all packages is $154,781.92
*Package 1 - Advanced Asphalt - $45,000 (Congress)
*Package 2 - Wil-Pav - $71,966 (English Landing)
*Package 3 - Advanced Asphalt - $19,800 (Line Creek)
*Package 4 - Corrective Asphalt (reclamite seal) - $18,015.92 (Gerner, PHHS and Union Chapel)
|
Legal References
:
|
N/A
|
Name of Persons(s) Submitting Agenda Item with Title
:
|
Jim Rich, Director of Operations
Dr. Paul Kelly, Assistant Superintendent for Business and Technology
|
Presenter(s) if Presentation Anticipated
:
|
N/A
|
Recommendation:
|
It will be recommended at the March 7, 2024 Regular meeting that the Park Hill Board of Education approve planned asphalt repairs, as presented.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Jim Rich - Director of Operations
|
|
Signed By:
|
|
Dr. Paul Kelly - Assistant Superintendent - Business & Technology
|
|
Signed By:
|
|
Dr. Mike Kimbrel - Superintendent
|
|
|
|
|
|
|
|